The Tarboro Water Treatment
Plant, built from 1937 to 1938, serves
approximately 14,000 people in Tarboro, NC, as
well as some of the surrounding rural areas.
Originally, the plant had rapid sand filters with
a total capacity of 1.5 mgd. It was upgraded in
1958 increasing the plant's capacity to 3 mgd. In
1979, the filters were converted to a dual-media
consisting of a nine inch layer of filter sand
beneath a twenty inch layer of filter anthracite,
again doubling the capacity to 6 million gallons
per day.
The most current rehabilitation begun in 1997 and
will be completed in 2000. Unifilt's portion of
the work on this project originally consisted of
the removal of the existing anthracite, and
replacement with a new Unifilt dual media
anthracite.
Work begun in the spring of 1999
with the removal of the anthracite in filter
number one. However, the project was placed on
hold due to a shortage of water during the warmer
months. Unifilt abated the dilemma by placing new
anthracite in only one filter and shutting down
the work for the summer.
While removing the anthracite from the first
filter, it became apparent to the experienced
Unifilt personnel on site that the support system
beneath the sand was mounded, and in a state where
failure was imminent. Further investigations by
Heyward, Inc, and The Wooten Company (the
Engineer) confirmed Unifilt's conclusions, and a
full replacement was requested.
Mother Nature then provided another obstacle for
the Tarboro Water Treatment Plant. On Labor Day,
Tarboro received approximately 10 inches of rain
which put the rivers at or above flood stage. Then
a week later on September 17th, Tarboro received
over 20 inches of rain in just a little over 24
hours sending the Tar River over its banks. The
experts called it a "500-year flood."
The first floor of the water plant was under
water, but fortunately no significant damage
occurred. The filters were not damaged, but
remained off line for seven days. The reservoir,
however, was unavailable for about a month.
Finally, Unifilt was able to return and complete
the total filter material replacement, including
ceramic balls, gravel, sand, and anthracite. With
the requirement that only one filter could be out
of service at a time, and the limited availability
of backwash water, this project was completed in
18 working days without disrupting plant
operation.
Unifilt is committed to completing all projects in
a professional and timely manner. Unifilt field
personnel have over 15 years experience in removal
and installation of filter media. Unifilt has the
capability to perform minor repairs to the
underdrain, and can completely change underdrains
when necessary.
Rely on Unifilt – call us toll free
1-800-223-2882. Unifilt understands your
challenges and is committed to exceeding your
expectations.